How long does it take?
  • Time frame depends upon a number of factors:
    • Scope of work
      • Minor electrical, mechanical, plumbing, roofing, siding, window, woodstove, and other permits don’t require a review and can be issued within an expedited time frame (issuance is determined by existing work load and other factors).
        • (ex: FAU replacements, sub panel replacements, etc.)
      • Work that requires plan review can take significantly longer.
        • Initial plan review takes 10-14 business days, whereas successive reviews typically take 5-7 business days.
        • The number and length of plan reviews are highly dependent upon the applicant's ability to respond accurately and adequately to the reviewers comment(s).  Failure to address specific review comments will significantly delay the review process.
        • A new Single-Family Residence can take anywhere from 6 months to more than a year to get through plan review.
        • A deck repair review typically takes approximately 2-6 weeks to be reviewed and issued.